Completed2018 to 2020
Indian Military Academy, Swimming Pool
Olympic size indoor swimming pool for the training of cadets
Dehradun
OTM accommodation, as the contract names it, at the Institute of Technology Management, with protective works, rewiring and repairs after heavy snowfall

Case study
Officers' living accommodation at ITM Mussoorie, built for the Military Engineer Services, Chief Engineer R&D, Delhi.
OTM accommodation under contract CA CE R&D/DLI-74 of 98-99, awarded at ₹111.25 Lac. Work began on 4 June 1999.
The building was handed over on 2 December 2000, a day before the contracted date, at a final value of ₹122 Lac. Three more jobs at ITM followed: protective works, finished 18 days early, the rewiring of its buildings, and the repair of cables brought down by heavy snowfall.
Time allowedTime takenContracted date

Completed2018 to 2020
Olympic size indoor swimming pool for the training of cadets
Dehradun

Completed2005 to 2007
Gymnasium seating 1,500, with a 59 metre span
Dehradun

Completed2020 to 2023
KLP for 14 Signal Regiment
Clement Town, Dehradun